SideMenu

WIND IPP PROJECTS

In 2008, we strategically diversified into the Wind Power Business, commissioning our first wind power project of 4.80 MW at Samana, Jamnagar in 2008 under a 20-year PPA executed with Gujarat Urja Vikas Nigam Limited (“GUVNL”) and have since, steadily expanded our presence in Gujarat. As on March 31, 2025, we own and operate 11 wind power projects in Gujarat, with a total installed capacity of 279.55 MW (“Operational Wind Power Projects”). In addition to our Operational Wind Power Projects, we are constructing two wind power projects of 104 MW in Gujarat that will take our IPP portfolio to a total installed capacity of 383.55 MW. These include:


-Orchid Phase I, a 51.30 MW project, which was secured at a fixed tariff of ₹ 3.70 per kWh pursuant to a Solar Energy Corporation of India (“SECI”) auction under Wind Tranche-XVI (“Orchid Phase I”); and


-Orchid Phase II, a 52.70 MW project, which was secured at a fixed tariff of ₹ 3.81 per kWh pursuant to a SECI auction under Wind Tranche-XVII, (“Orchid Phase II” and together with Orchid Phase I, referred to as the “Under Construction Projects”).


The table below sets forth a summary of our Operational and Under Construction Wind Power Projects as of March 31, 2025:

Project Name / Location Total Installed Capacity (MW) Date of Commissioning / Expected Date of Commissioning PPA Customer/Contracted Capacity (MW) PPA Tenor (years) Applicable Tariff PLF(%) Generation (kVh in millions)
  Fiscal Fiscal
  (Rs./kWh) 2025 2024 2023 2025 2024 2023
Operational Wind Power Projects
Jamnagar Wind Farm /Gujarat 4.80 (6 x 0.8) April, 2008 GUVNL /4.8 20 3.37 18.21% 19.92% 19.39% 7.66 8.40 8.15
Jangi-Vandhiya Wind Farm-Phase I / Gujarat 14.85 (9 x 1.65) March, 2010 GUVNL /14.85 25 3.56 15.43% 18.10% 16.64% 20.07 23.61 21.65
Jangi-Vandhiya Wind Farm-Phase II / Gujarat 9.90 (6 x 1.65) January, 2011 GUVNL / 9.9 25 3.56 12.82% 15.50% 13.61% 11.12 13.48 11.81
Jangi-Vandhiya Wind Farm-Phase III / Gujarat 21.60 (12 x 1.8) July / December, 2011 GUVNL / 21.6 25 3.56 21.39% 21.61% 22.01% 40.47 41.00 41.65
Jangi-Vandhiya Wind Farm-Phase IV / Gujarat 25.20 (14 x 1.8) February / March, 2012 GUVNL / 25.2 25 3.56 23.42% 25.47% 24.10% 51.69 56.38 53.21
Jangi Wind Farm / Gujarat 22.00 (11 x 2) June / July, 2014 GUVNL / 22 25 4.15 20.61% 21.72% 20.72% 39.72 41.97 39.92
Goinj Wind Farm / Gujarat 18.00 (9 x 2) March, 2015 GUVNL / 18 25 4.15 24.62% 24.55% 24.36% 38.83 38.82 38.40
BDS Wind Farm / Gujarat 10.00 (5 x 2) January / February, 2017 GUVNL / 10 25 4.19 31.36% 29.65% 32.46% 27.47 26.05 28.43
Bhatel Wind Farm / Gujarat 50.60 (23 x 2.2) January, 2019 GUVNL / 50.6 25 2.44 29.92% 32.02% 30.70% 132.63 142.33 136.07
Rajkot Wind Farm / Gujarat 51.30 (19 x 2.7) October, 2020 GUVNL / 50.6 25 2.80 32.44% 34.42% 33.41% 145.79 155.12 150.15
Khambhaliya Wind Farm SECI – VI Gujarat 51.30 (19 x 2.7) March, 2022 SECI / 50.6 25 2.82 31.26% 33.13% 21.04% 1140.46 1149.29 78.24
Total 279.55                    
Under Construction Wind Power Projects
Orchid - I SECI XVI/ Gujarat 51.3(19 x 2.7) By the end of September 2025 SECI / 50 25 3.7 - - - - - -
Orchid - I SECI XVII/ Gujarat 52.7 (17 x 3.1) By the end of September 2026 SECI / 50 25 3.81 - - - - - -
Total 104.00                    


In addition to our Under Construction Projects, the following table sets out our Pipeline Projects that are part of our IPP portfolio:


S No. Project Name / Location Capacity (MW) (Wind Power) Capacity (MW) (Solar Power)
1. Project Alpha / Gujarat 50.0 -
2. Project Beta / Gujarat 100.0 30.0
3. Project Gama / Gujarat 100.0 -
Total 250.0 30.0

Note: Generation numbers are recorded at the billing meter end…. The weighted average PLF of our fleet operating in the range of 26% to 28.5% yearly.


“Pipeline Projects” refer to projects where we have applied for the connectivity for the project and have initiated other preliminary project development related activities like installation of wind mast, land acquisition etc.



With over 15 years of experience in the wind power sector, we have established a strong track record of identifying, developing, constructing, and operating wind power projects, with a sustained focus on supplying renewable energy to state and central distribution utilities. Our Operational Wind Power Project portfolio of 11 projects is supported by long-term, fixed-tariff PPAs with GUVNL and SECI, generally with a term of 25 years. As of March 31, 2025, the weighted average of the remaining contracted years of life of these PPAs is 17 years. Under the executed PPAs, we prioritize supplying electricity to Gujarat discoms and, via SECI, to distribution utilities in Uttar Pradesh and Bihar. These PPAs help to ensure a stable and timely receivables cycle. Our receivable days as part of our Wind Power Business for Fiscals 2025, 2024 and 2023 were 47 days, 60 days and 39 days, respectively. To further enhance payment security, we have opted for a payment security mechanism under the PPAs entered with SECI. Specifically, this includes an unconditional, revolving and irrevocable letter of credit as a payment guarantee from SECI. For our Under Construction Projects, this mechanism was implemented with a discount of ₹0.02 per kWh on monthly billings under the PPA. For our Operational Wind Power Project, Khambhaliya Wind Farm SECI – VI, Gujarat, this security is provided at no additional cost.


GE Vernova. We began our association with GE Vernova in the Wind Power Business in 2019. Since then, we have successfully commissioned two wind power projects with GE Vernova WTGs, with an aggregate installed capacity of 102.60 MW as of March 31, 2025. Furthermore, as of March 31, 2025, we have one project under construction with an aggregate installed capacity of 51.3 MW, with WTG supply arrangement with GE Vernova.


Vestas. We started our association with Vestas in the Wind Power Business in 2010 and over the years we have implemented eight wind power projects having an aggregate installed capacity of 172.15 MW with WTGs attributable to Vestas. Vestas also provides O&M and other related services in relation to these projects. Furthermore, in 2024, we signed a framework agreement with Vestas for the supply of multi-model spare parts in India. This agreement covers spare parts suitable for WTGs manufactured by OEMs other than Vestas, for the Indian market, allowing us to strengthen our position in the Indian aftermarket for WTGs spare parts.


In relation to our Wind Power Business, our experienced in-house team oversees the project lifecycle, including design, sizing, engineering, development, construction, and operations of our wind power projects, enabling us to ensure quality control and cost efficiency.


Our performance across these operating parameters has further translated into average plant load factor (“PLF”, i.e., total electricity generation from fully operational capacity divided by the maximum possible generation from the same capacity during the period of operation) across our Operational Wind Power Projects portfolio, as illustrated below:


We have an integrated and disciplined approach to developing wind power projects, with capabilities and in-house resources to implement a project from the stage of WRA to commissioning. We mitigate operating risks through a structured and well-established project development and selection process. In order to avoid delays and bottlenecks that commonly affect project execution timelines and power evacuation capabilities, we aim at identifying and addressing potential challenges at the inception stage of project planning. Our approach includes a detailed analysis of long-term wind resource data obtained from multiple on-site wind masts to ensure generation reliability. We also conduct external and internal micro siting studies, along with meticulous project layout planning, to minimize the negative impact caused when wind turbines are positioned close together and disrupt each other’s airflow (known as the ‘wake effect’) and optimize energy output.


To ensure reliability and minimize transmission-related downtime, we use double circuit transmission lines and provide transfer buses in substations. Moreover, our ability to connect large-scale wind capacities to pooling substations (“PSS”) allows us a wider margin for variation in energy output, which leads to more accurate forecasting and fewer penalties for deviation.


Wind farms registered under the UNFCCC for clean development mechanism:


Our wind power projects aggregating to a total installed capacity of 264.85 MW located in Gujarat, are currently registered under the United Nations Framework Convention on Climate Change (“UNFCCC”). Consequently, our registered wind farms may generate and sell certified emissions reductions (“CERs”) under the Kyoto Protocol’s Clean Development Mechanism (“CDM”) project. The current clean development mechanism status of the relevant wind power projects is indicated in the table below:


Wind Farm Annual Installed Capacity (MW) as of March 31, 2025 Status
Jangi-Vandhiya Wind Farm 14.85 Registered on Verra
Jangi-Vandhiya III Wind Farm 21.6 Registered on Verra
Jangi-Vandhiya IV Wind Farm 25.2 Registered on Verra
Jangi, Gujarat Wind Farm 22 Registered on Verra
Goinj Wind Farm 18 Registered on Verra
BDS Wind Farm 10 Registered on Verra
Bhatel Wind Farm 50.6 Registered on Gold Standard
Rajkot Wind Farm 51.3 Registered on Gold Standard
Manza Wind Farm 51.3 Registered on Gold Standard

WIND IPP PROJECT LOCATOR